How long does an apartment renovation take in Barcelona

Timelines by type of job, the stages they’re made of, and what most often causes delays.

In short: bathroom 2–4 weeks, kitchen 3–5 weeks, turnkey studio about 3 months, 60–80 m² apartment 3–5 months, 100+ m² 4–6 months. Plus design and permit time if the layout changes.

Timelines by job

JobWork time
Turnkey bathroom2–4 weeks
Turnkey kitchen3–5 weeks (the made-to-measure kitchen is built in parallel)
Cosmetic renovation1–2 months
30 m² studio, turnkeyabout 3 months
60–80 m² apartment, turnkey3–5 months
100+ m² apartment, turnkey4–6 months

The stages

  1. Design — 1–6 weeks, from a layout to a full 3D project. Design project →
  2. Permit — from zero days to about 2 months. Details →
  3. Demolition and removal — about a week.
  4. First fix — 3–6 weeks: new walls, electrics, pipes, levelling.
  5. Finishes — 4–8 weeks: tiles, floors, paint, ceilings, doors.
  6. Furniture and appliances — 1–2 weeks of fitting. Made-to-measure items take weeks to make, so we order right after measuring.
  7. Cleaning and handover — a few days.

What most often causes delays