How long does an apartment renovation take in Barcelona
Timelines by type of job, the stages they’re made of, and what most often causes delays.
In short: bathroom 2–4 weeks, kitchen 3–5 weeks, turnkey studio about 3 months, 60–80 m² apartment 3–5 months, 100+ m² 4–6 months. Plus design and permit time if the layout changes.
Timelines by job
| Job | Work time |
|---|---|
| Turnkey bathroom | 2–4 weeks |
| Turnkey kitchen | 3–5 weeks (the made-to-measure kitchen is built in parallel) |
| Cosmetic renovation | 1–2 months |
| 30 m² studio, turnkey | about 3 months |
| 60–80 m² apartment, turnkey | 3–5 months |
| 100+ m² apartment, turnkey | 4–6 months |
The stages
- Design — 1–6 weeks, from a layout to a full 3D project. Design project →
- Permit — from zero days to about 2 months. Details →
- Demolition and removal — about a week.
- First fix — 3–6 weeks: new walls, electrics, pipes, levelling.
- Finishes — 4–8 weeks: tiles, floors, paint, ceilings, doors.
- Furniture and appliances — 1–2 weeks of fitting. Made-to-measure items take weeks to make, so we order right after measuring.
- Cleaning and handover — a few days.
What most often causes delays
- Deliveries. Windows, doors, custom furniture. In our Gavà project the supplier “lost” the windows for a month — so we order early and track it ourselves.
- Changes on the fly. Every “let’s redo this” costs days. A design up front saves weeks.
- Hidden problems. Rotten pipes or old wiring only show after demolition. An experienced contractor allows for it.
- The permit. Filed late, the crew waits.
- August. Many Spanish suppliers close for holidays — we plan around it.